A2 Świecko - Konin | Every kilometer matters
From March 1st, it is planned to construction passageways on the section Poznań West – Poznań Luboń and the entry lanes at the Poznań Luboń interchange.
A temporary traffic organization will be introduced on the indicated sections of the motorway.
Schedule of works:
Poznań Komorniki Interchange: construction of two passageways in length 158km+650 – 158km+730 and 160km+160 – 160km+240
(scheme 4.1 b)

Poznań Luboń Interchange: construction of two passageways in length 163km+860 – 163km+940 and 164km+145 – 164km+245
(scheme 4.1 c)

Poznań Luboń Interchange: construction entry lanes in length 163km+790 – 163km+950
from 1.03 from 8pm to 4.03 to 6am or from 8.03 from 8pm to 11.03 to 6am)
(scheme 4.1 d))

Works beetween the Poznan West Intechange and Poznań Komorniki Interchange: construction of three passageways in length: 155km+ 700 – 155km+780, 156km+270 – 156km+350 and 156km+700 – 156km+780.
There will be two lanes in use, vehicles from the fast lane will be going on a slow lane, and vehicles from a slow lane will be going on the emergency lane.
(scheme 4.1 a)

Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number: 0 800 022 242