Rehabilitation of pavement at the Trzciel Interchange

6 May is the scheduled commencement date for the pavement rehabilitation at the Trzciel Interchange on the motorway (around 91 km of A2 ). The works will result in detours being established in individual phases of works. Drivers are requested to drive safely and to abide by the temporary traffic organization signage and marking.

Autostrada Wielkopolska II is commencing rehabilitation works at the Trzciel Interchange (around 91 km of A2 ) In order to minimize the construction’s impact on drivers, the works have been phased.

Phase I will begin on 6 May and will include replacement of the wearing course on the exit roads from the motorway. This means no exit from A2 at the Trzciel Interchange.

Following detours will be available as of 6 May:
• For the drivers traveling from Świecko the detour leads through the Jordanowo Interchange, the S3 Expressway up to the Świebodzin Północ (North) Interchange. Further, on DK92 road to Trzciel.

• The drivers traveling from Świecko and willing to leave the motorway in the direction of Zbąszyń should choose the detour leading through the Jordanowo Interchange, the S3 Expressway up to the Świebodzin Północ (North) Interchange and further on the DK92 road to the county road 1213F to Zbąszyń.

• For the drivers traveling from Poznań, the detour leads through the Nowy Tomyśl Interchange, on the provincial road 305 to the roundabout in Miedzichowo. Further on DK92 road to Trzciel or on provincial roads 305 and 302 to Zbąszyń.

• For the drivers traveling on A2 from Poznań, in the direction of Zbąszyń, the detour leads through the Nowy Tomyśl Interchange, on the provincial road 305 to the roundabout in Miedzichowo. Further on the provincial road 305 to road 302 leading to Zbąszyń.

The estimated duration of the pavement rehabilitation works on the exit roads (Phase I) is ca. two weeks. After completion, the works will move to the entry slip roads, which will be announced in a separate communication.
Autostrada Wielkopolska II S.A. obligated the contractor to complete the works on time. It must, however, be remembered that inclement weather may result in extension of the completion deadline.