Pavement rehabilitation at the Jordanowo Interchange (A2 km 68+710)

25 September is the scheduled commencement date for the pavement rehabilitation at the Jordanowo Interchange (A2 km 68+710). The works will result in detours being established in individual phases of works. Drivers are requested to be alert and to abide by the temporary traffic organization signs.

In line with its long-term maintenance program, Autostrada Wielkopolska II is commencing rehabilitation works at the Jordanowo Interchange (A2 km 68+710). In order to minimize the construction’s impact on drivers, the works have been phased.

Phase one will begin on 25 September and will include replacement of the wearing course on the exit slip roads of the interchange. Therefore, drivers traveling on the A2 motorway and willing to exit to S3 expressway will have to use the prepared detours.

  • The detour for drivers traveling from Świecko will run through the Torzym interchange, on the district road 138 up to its intersection with the national road 92 in Torzym, further on the road 92 to the roundabout on the Świebodzin bypass, community road leading to the “Świebodzin Północ (North)”interchange or even further to the “Świebodzin Południe (South)” interchange.

  • For the drivers traveling from Warsaw, the detour will run through the Nowy Tomyśl interchange (for vehicles with GVW>7t) or through the Trzciel interchange (only for GVW<7t).

From the Nowy Tomyśl interchange (GVW>7t) the detour runs along the district road 305 to the roundabout in Bolewicko, further onto the national road 92 to the Świebodzin bypass and then to the Świebodzin Północ or Świebodzin Południe interchange.

Drivers who take the exit at the Trzciel interchange (GVW<7t) will continue on county roads to national road 92, further towards the Świebodzin bypass and then to the Świebodzin Północ or Świebodzin Południe interchange

The works on exit slip roads are estimated to take ca. 16 days. Autostrada Wielkopolska II obligated the contractor to timely complete the works. It must, however, be remembered that inclement weather (high wind, heavy rainfall) may affect the completion date.
After the exit slip roads have been rehabilitated, works will be moved to the entry slip roads. We shall notify the drivers about that phase separately.