Construction news
-
THE MOTORWAY TO ŚWIECKO ALREADY OPEN!
13.01.2012 - 10:16
On 1 December 2011 Poland became connected to the European motorways network Zobacz więcej »
-
Concrete paving on the whole A2 Motorway section to Świecko completed!
06.10.2011 - 11:19
It is only two months left until the official opening of the A2 motorway leading to the border with Germany. We can already announce the completion... Zobacz więcej »
-
Progress of construction works of A2 Motorway to Świecko on the end of September 2011
05.10.2011 - 13:58
Road works:
Completed by October 5th 2011:
- lean concrete roadbase - finished
- PPC surface course - 99%, 1 km to be done Zobacz więcej » -
Polish Road Bicycle Racing Championships on the A2 motorway to Świecko!
03.10.2011 - 15:13
It is less than two months left to the official opening of the motorway, and A2 has been taken over by the bicycles already. Zobacz więcej »
-
Progress of construction works - August 25th 2011
25.08.2011 - 10:51
Progress of construction works of A2 Motorway to Świecko on August 25th 2011 Zobacz więcej »
-
Progress of construction works - August 2nd 2011
02.08.2011 - 12:56
Progress of construction works of A2 Motorway to Świecko on August 2nd 2011 Zobacz więcej »
-
Progress of construction works - July 18th 2011
18.07.2011 - 10:00
Progress on construction of A2 Motorway Świecko - Nowy Tomyśl on July 18th 2011 Zobacz więcej »
-
Progress of construction works - June / July 2011
15.07.2011 - 12:00
Progress of construction on the section of A2 Motorway between Świecko and Nowy Tomyśl as at the end of June and beginning of July 2011. Zobacz więcej »
-
Progress of construction works - May 2011
29.05.2011 - 13:08
Following the latest summary of the construction works progress in A2 motorway to Świecko (105.9 km) we inform that in compliance with the report o... Zobacz więcej »
-
The progress of construction works - May 2011
15.05.2011 - 10:00
In six months, we will be able to get to Berlin quickly and conveniently, using the A2 motorway. Zobacz więcej »